Reception Building internal concrete being poured into Mixing Room floor
New tensioning wire for final tensioning of both Digesters
Outside Digester 1
Inside Digester 1
Digester view 02
Digester view 01
Both Digesters now constructed and under tension awaiting curing
Digester internal view
Each of the visible holes will have a tensioning wire running through
Wire tensioning machine
Temporary tensioning wire for tank construction
Digester tank construction begins. Each Digester is made up of 48 precast concrete panels
Both Digester bases now fully concreted
Reception Building internal layout in construction
Digester 1 concrete base poured and steel reinforcement to Digester 2 in place
Steel reinforcement for Digester 1 base
Reception Building external showing Mezzanine Floor access and windows
Reception Building internal 02
Reception Building internal 01
Reception Building now steel cladded and both Digester bases awaiting steel reinforcement prior to concreting
More Digester base excavation and Containment Bund Wall progress
Containment Bund Wall progress
Digester bases excavated
Northern Power Grid Substation foundation poured
Reception Building foundations poured B
Reception Building foundations poured A
Containment Bund Wall commenced construction
Reception Building foundations excavated
Site clearance and levelling
Digestate Lagoon awaiting leak detection system
Construction site setting up